Section B: 1977
1977 was the year of Job Creation. A second workshop scheme ran from February to September and later in the year the third and fourth
schemes until March 1978 and December 1978 were agreed. Work started on Gateshead 5 in August 1976. Its trucks were in poor condition and
were stripped down and rebuilt. The windows and exterior panels were removed and replaced or refurbished. The interior was refurbished in
the ornate Gateshead pattern and the car was rewired. New air tanks were delivered in April and 5 made its debut on Members’ Day in May 1977.
218 ABOVE & 219 BELOW. Two views of the partially completed Gateshead 5 early in 1977.
220. The first two ‘Job Creation’ cars at Wakebridge in the summer of 1977 with Prague 180 in the background.
Blackpool 49 was the third Job Creation project with work starting towards the end of 1976. Its trucks required no major work other than
armature work and wheel profiling. On the body a distorted body side was corrected, under frame cross members and the lower saloon floor were
replaced. The car was rewired throughout, the entire interior was renovated and the lower deck seats were reupholstered. The exterior was
repainted in the green and cream livery it still carries and it entered service on 25th June.
Glasgow 1282 entered the workshop early in February and was recognised to be the most demanding job yet. It was lifted from its trucks using
specially designed brackets and the trucks were stripped down. All the top deck body panels were removed and replaced as necessary after
repairs to the frame. The lower saloon and under frame were tackled next. Extensive corrosion necessitated the replacement of many
components and extensive welding. The main body posts were replaced as were both driving cabs and platform areas. The controllers
and the electrical contactor units were overhauled and the car was completely rewired. 1282 was reunited with its trucks early in
December and made its first test run on December 15th. Scottish members were deeply involved in this project carrying out research
and producing working drawings.
221 ABOVE & 222, 223 BELOW. Three views of Blackpool 49 and Glasgow 1282 in the workshop.
224. Blackpool 49 in August 1973 – the last season it ran in the red livery.
225. The newly restored Blackpool 49 on the washbay four years later.
Paisley 68 was the fifth Job Creation project and entered the workshop in September. Its truck was overhauled without problems but
corrosion was found on the body under frame. The components of the steam tram returned to Crich on 15th November. Another Job Creation project
was the horse drawn tower wagon. Manchester 765 received a touch up and varnish job by the Job Creation team. It entered service after a launch
party on 30th April.
Leeds 602 was decorated to celebrate the Queen’s Silver Jubilee. It will be remembered that 602 was delivered in Coronation year and carries a
livery of Royal Purple. Newcastle 102 was withdrawn following an accident early in July. Work continued with the paintwork on Southampton 45 and
Blackpool 166 had its paintwork renovated.
226. Manchester 765 and Johannesburg 60 on the depot fan.
227. Blackpool 166 being used as a mobile bandstand at the 1977 Extravaganza.
228. Leeds 602 standing in Depot II in August 1977. Note that the overhead line is in place but that not quite all of the depot floor
has been concreted.
The following list of stored trams was compiled in November 1977. Clay Cross store – Blackpool 1 (now 4), Blackpool works car 2, Blackpool
omo 8, Fleetwood box 40, Cardiff 131, Gateshead 52, Grimsby & Immingham 14, Howth 10, Derby 1, Blackpool 641 (304). Clay Cross yard – bodies of
Chesterfield 7, Maidstone demi-car 18 and an unidentified Hull car. Crich Depot V – Blackpool 167, Cheltenham 21, Glasgow cable car 1, Hull 132,
Leeds 345 & 399. Crich Derwent View – Blackpool 158. Bonwell Street London – LCC 106, parts of North Metropolitan horse car 39 and Rawtenstall 23.
Green Lane Depot Liverpool – Liverpool 869. Blackpool Corporation car sheds – Blackpool 59. Blackpool College of Technology – Blackpool 298. Note
Derby 1, Blackpool 641 and Rawtenstall 23 were not owned by the TMS.
The hand crane was rebuilt during the winter of 1976-77 using the existing crane mechanism with detailed enhancements on a newly fabricated
steel truck, with wheelsets from Liverpool and rubber suspension blocks from a Blackpool coronation tram.
229. The truck for the ‘new’ crane. The old crane can be seen in picture 184 above.
230. The new crane in use at Wakebridge.
The iron railings from Armley Road Schools in Leeds were dismantled by a working party on 19th February and placed in storage at Crich
for future use alongside the depot fan. Work continued on replacing the rails and concreting the floor of Depot II. Part of the bank side
opposite Depots V and VI was bulldozed to enable a track connection to Depot V. The large wooden falcon that had adorned the Brush factory
was also acquired and placed in storage.
231. Depots V and VI looking very neat.
232. A recent view of the Brush falcon in the exhibition hall.
Following a chance meeting at the reception in November 1976 to mark the completion of Johannesburg 60, negotiations were started with
the landowners, the Clay Cross Company to obtain a more secure tenure of the line to Wakebridge and possibly to extend the line beyond
Wakebridge. Surveys were carried out in December 1976 and January 1977 in snow and rain to determine whether to climb the hill, continue
on the Wakebridge level or have a down gradient. By the end of May agreement was reached for a wayleave over the land for the upper route,
planning approval had been received and the Railway Inspectorate had given its approval in principle.
Detailed plans were drawn up showing the earthworks required through what was described as hostile territory. The Manpower Services
Commission approved a grant of £38,000 for another Job Creation Programme to construct the line once the way had been cleared. A committee
consisting of Maurice O’Connor, Michael Davis, Bob Hall and Richard Hartwell was set up to co-ordinate the work with Bob having responsibility
for day to day matters. The work was planned to be undertaken between June 1977 and March 1978 with an estimated 700 man weeks work. Messrs
Tomlinson and White were awarded the earth moving contact and started work immediately after Spring Bank Holiday Monday. Explosives were
used on about 40 feet of bed rock. The contract also included spreading and levelling five inch ballast underlay on the whole of the track
formation. The route has a maximum gradient of 1 in 30.
233 ABOVE & 234, 235 BELOW. Three pictures of the bulldozer at work.
236. Looking down the newly bulldozed route with Blackpool 49 at Wakebridge terminus in the back ground.
A preliminary team of eight men started work under the Job Creation Scheme on 13th June and their first task was to establish a base
camp at Wakebridge. The Bradford shelter was used as a mess room and two ex-BR box vans were acquired for storage. Rail was taken from the
stock pile in the car park and welded together into 60 foot lengths. All the stock of traction poles was stripped, cleaned and painted as
was ex-Nottingham scroll work for the bracket arms. An appeal for funds to purchase good quality concrete sleepers had been launched and
the first had been received and placed in position by the end of August when the labour force had grown to 13.
237. Looking up the new line from Wakebridge.
238 ABOVE & 239 BELOW. Two views looking down towards Wakebridge in the autumn of 1977.
By the end of November, the track and sleepers had been laid as far as the beginning of Glory Mine loop. Traction poles had been
erected alongside the line and bracket arms complete with ornamental work were being added. The body of Glasgow W21 was moved to Wakebridge
for use as an electricians workshop.
In addition to the track the project included the construction of a new electrical sub-station. Agreement had been reached with the East
Midlands Electricity Board for an 11 kV supply and both EMEB and TMS switch gear were to be housed in different parts of the same building. The
ex Walsall transformer rectifier unit was to be installed at track level above the building. By the end of November the inner walls built
from Aglite blocks was complete and work was in hand on the stone built outer walls.
240. The impressive looking new track half way up the hill. The new line opened up wonderful views of the Derbyshire countryside.
241. Looking down the line from Glory Mine.
242. Looking up the line towards Glory Mine.
243. The beginnings of Glory Mine loop.
244. A recent view of Wakebridge sub-station.
Two additional Job Creation projects were approved for 1978 for improvements to Visitor Reception and for an Edwardian Street,
but more of these later.
Admission prices in 1977 were 50p adults and 30p children. These were increased for 1978 to 60p Adults and 40p children. During 1977, a series
of Operations Handbooks mainly for tram crews were prepared by Gwynne Thomas and updated versions are still in use.
13 passenger trams were used in 1977. Blackpool 40, 49, 166, Gateshead 5, Glasgow 22, 1297, Johannesburg 60, Manchester 765, Newcastle 102,
Prague 180, Sheffield 264, 510 and Vienna 4225.
245. A picture of the Hall, Hartwell and Lomas children playing in the snow early in 1977.
246. Iain Lomas at the controls of Johannesburg 60 during the summer.
247. Special postal cover featuring Leeds 602.
Richard Lomas
2nd November 2010
To be continued . . .
This page continued from part 6a. To return to 6a
CLICK